Sprinkler Requirements

  • Required on all new construction
  • Must be designed by a licensed engineer.
  • Must be installed by a State Licensed Sprinkler Contractor
  • Three sets of prints are required.
  • There is a plan review fee of $100, plus $1 per head.
  • 13R required on all new condos, apartments, and townhomes.
  • The MFD does allow Blazemaster in basements, provided proper construction protocols have been met.
  • FDC to be 5” Storz, with Knox locking cap and 30 degree elbow, locking cap can be purchased online at www.knoxbox.com
  • FDC shall be located on the front of the building.
  • Outside strobe is required instead of bell.
  • Call ahead 24 to 48 hours for test.

If you require further information please email fdbureau@mundelein.org. A representative will get back to you as soon as possible.